Full Text
HIGH COURT OF DELHI
Date of Decision: 06th FEBRUARY, 2026 IN THE MATTER OF:
M/S DYNAMIC PROJECTS .....Petitioner
Through: Mr. A. K. Tewari, Mr. Rahul Burman and Ms. Yosha Dutt, Advs
Through: Mr. Vinay Yadav, CGSC with Advocates Ms Kamna Behrani, Mr. Ansh Kalra and Mr. Neeraj Paulose with Mr. A. K. Pandey, Director, and
Mr. M. K. Goyal, Joint Director, and Mr. R. Kayasth, TLC, DGMAP
JUDGMENT
1. The present petition has been filed under Section 11(6) of the Arbitration and Conciliation Act, 1996 by the Petitioner seeking appointment of an Arbitrator to adjudicate upon the disputes which have arisen between the parties under a Contract dated 22.05.2009.
2. The facts, as narrated in the petition, are that the Respondent No.1 invited bids for the work of “Detailed Engineering and Project Management Consultant for construction of residential accommodation at Karwar (Navy)”. The Petitioner participated in the tender. The bid of the Petitioner was accepted and the Contract was awarded to the Petitioner.
3. It is the case of the Petitioner that the work stood completed on 15.01.2018. The Petitioner, thereafter, on 21.11.2023 submitted its running account bill amounting to Rs.20,08,818.00/- to Respondent No.3 for Stage- IV under the Contract. Further on 08.01.2025, the Petitioner submitted its bill amounting to of Rs. 2,42,34,215.00/- to Respondent No.3 for Stage-V (Final stage) under the Contract. It is stated that since the bills submitted by the Petitioner for Stage-IV and Stage-V were not cleared, disputes arose between the parties.
4. It is stated that the Petitioner, thereafter, issued a notice under Article 17 of Contract requesting the Engineer-in-Chief, Integrated HQ of MOD (Army), Kashmir House, Rajaji Marg, New Delhi (who is the designated authority to appoint a Sole Arbitrator) to appoint an independent and impartial Arbitrator. Since no response was received, the Petitioner approached this Court by filing the present Petition seeking appointment of an Arbitrator to adjudicate upon the disputes.
5. Notice was issued in the Petition on 15.09.2025.
6. It is stated by the learned Counsel for the Respondents that the Petitioner failed to perform its duties under the Contract. According to the Respondents, the arbitration clause, which is Article 17 of the Contract, could be invoked only after the completion of defect liability period of two years. He states that a similar arbitration clause was the subject matter of challenge before this Court in another petition under Section 11 being ARB
Court appointing an Arbitrator in that petition was the subject matter in an Special Leave to Appeal (C) 17079/2024, wherein the Apex Court set aside the Order of the learned Single Judge appointing an Arbitrator.
7. Heard learned Counsel appearing for the Parties and perused the material on record.
8. The main question which arises for consideration before this Court is as to whether the invocation of arbitration by the Petitioner was invalid and/or premature. It is necessary to reproduce Article 17 of the Contract, which is the arbitration clause under the Contract. The same reads as under:- “ARTICLE 17 SETTLEMENT OF DISPUTES All disputes, between the parties to the contract (other than those for which the decision of the DGMAP or any other person is by the contract expressed to be final and binding) shall, after written notice by either party to the Contract to the other of item, be referred to the sole arbitration of serving officer having degree in Engineering or equivalent or having passed Final / Direct Final Examination of Sub Division II of Institution of Surveyors (India) recognized by the Govt of India to be appointed by the Engineer-in-Chief, Ein-C's Branch, Kashmir House, New Delhi-11 or Director General of Works if specifically delegated in writing by Engineer-in-Chief, Army Headquarters, New Delhi whose decision shall be final, conclusive and binding. The Arbitration shall be governed by Arbitration and Conciliation Act, 1996. Unless both parties agree in writing, such reference shall not take place until after the completion or alleged completion of the Works or termination or determination of the Contract under conditions of this contract. Provided that in the event of abandonment of the works or cancellation of the Contract under conditions of this contract, such reference shall not take place until alternative arrangements have been finalized by the OWNER to get the works completed by or through any other consultant or consultants or Agency or agencies. Provided always that commencement or continuance of any arbitration proceeding hereunder or otherwise shall not in any manner militate against the Owner's right of recovery from the consultant as provided in conditions of this contract. If the Arbitrator so appointed resigns his appointment or vacates his office or is unable or unwilling to act due to any reason whatsoever, the authority appointing him may appoint a new Arbitrator to act in his place. The Arbitrator may proceed with the arbitration, exparte, if either party, inspite of notice from the Arbitrator, fails to take part in the proceedings. The Arbitrator shall give his reasoned award in writing on all matters referred to him and shall indicate his findings, along with sums awarded, separately on each individual item of dispute. The venue of arbitration shall be such place or places as may be fixed by the Arbitrator in his discretion. The language of the arbitration proceedings and that of all documents any communications between the parties shall be "English". The award of the Arbitrator shall be final and binding on both the parties to the contract. Notwithstanding the fact that the stations of work are anywhere in India, only the courts at Delhi/New Delhi shall have the jurisdiction to adjudicate and settle any disputes between OWNER and the consultant. No other court outside Delhi/New Delhi shall have any jurisdiction on any matter requiring reference to Civil Court.”
9. This Court has also gone through the Order dated 04.03.2024 passed by the learned Single Judge of this Court in ARB.P. No.1342/2022, which has been relied on by the Respondents. A perusal of the said Order brought out notable factual dissimilarities from those involved in the present petition. Parts of the Order depicting such disparities are extracted as under:-
14. Further, the petitioner‟s contention is that it had already terminated the contract on 14.09.2021 and thereafter the cancellation of the contract by the respondent is a farce and an attempt to build up a defence. Further, it is pointed out that the period of the contract had also come to end before reference was sought. In this context, the Jammu and Kashmir and Ladakh High Court in Mohindra Bros (supra), has held as under: “Perusal of Condition 70, read as whole, demonstrates its object that arbitration may not be permissible during the period of Contract unless there was agreement between the parties for reference to arbitration or in the event of abandonment of Works or cancellation thereof, until alternate arrangements were finalized by the Government to get the Work completed by or through any other Contractor or Agency. The completion of Contract referred to in the Condition means the period initially fixed for completion of Contract, of course, including the extended period thereto. After the expiry of the period of Contract or extension allowed therefor, the agreement of the parties and the Proviso appended to Condition 70 thereof may not have any application, in that, after the expiry of period of Contract or extended period thereof, resort to arbitration is permissible for referring the matter to arbitration. Abandonment, cancellation or completion of work by any other Contractor or Agency would also not operate as impediment for appointment of Arbitrator when the period of Contract had otherwise expired.”
15. The above observations in Ivrcl (supra) and Mohindra Bros (supra), are squarely applicable in the present case. Also, the respondent cannot be permitted to frustrate the arbitration agreement by failing to make the alternative arrangements for inordinately long period. Almost two years have expired since the date of cancellation of the contract and the alternative arrangements are apparently not yet in place. In this context, the Punjab and Haryana High Court in Sai Enterprises (supra), has held as under:
10. The abovementioned Order demonstrates that the facts in ARB P. NO. 1342/2022 and the facts in the present case are distinguishable.
11. To summarize, the facts in ARB P. No. 1342/2022, reveal that since the work was not completed, several notices were issued by the Respondent complaining that the progress in work was extremely slow and, thereafter, on 21.01.2022, the contract was terminated.
12. Upon being directed by this Court, a copy of the Special Leave to Appeal (C) 17079/2024 was handed over in Court, which contains the letter of termination dated 21.01.2022 and is being reproduced as under: “Dear Sir,
1. References:- (a) This HQ latter No 84841/MAP/PH-II/PKG- 28/ Mumbai (Army)/957/E[8] dt 30 Jul 2021. (b) This HQ letter No 34841/MAP/PH-1I/PKG- 28/ Mumbai (Army)/980/E[8] dt. 16 Nov 2021. (c)This HQ letter No 84841/MAP/PH-II/PKG- 28/ Mumbai (Army)/1005/E[8] dt 14 Jan 2022.
2. In spite of notices Issued to you under the references mentioned at para 1 (a) and (b) in connection with the work to be executed under the above mentioned contract, you have failed to recommence the work after, you abandoned it since Jun 2021.
3. Therefore, I Accepting Officer of the contract, on behalf of the Government, acting under the powers vested in me in terms of condition 48 of the General Condition of Contracts and without prejudice to any other right of remedy which shall have accrued or shall accrue hereinafter to the Government under the terms of the above said contract, hereby cancel your this contract on account of your default and the said contract shall stand cancelled with Immediate effect.
4. Please note that the remaining works as defined in the contract condition 1 (c) of the General Conditions of Contracts will be completed by me through another agency at your risk and cost.
5. You are accordingly requested to report to PM at his office in person or through an accredited representative on the date to be intimated by PM when an Inventory of complete/incomplete items of work and materials, if any, left by you at site will be made and recorded jointly. In the event of your failure to keep this appointment, Inventory will nevertheless be prepared notwithstanding your absence and the same shall be fully binding on you.
6. This is without prejudice. Yours faithfully (J S Ishar) Maj Gen DG MAP”
13. Unlike ARB P. No. 1342/2022, in the present case, the works stand completed by the Petitioner. In fact, a Completion Certificate dated 17.02.2028 has also been issued to the Petitioner which reads as under:
14. On account of the facts being entirely different in ARB P. NO. 1342/2022, the Order passed by this Court in ARB P. No. 1342/2022 and its subsequent overruling is wholly misplaced, as the work was terminated in the said case whereas, in the present case, the work stands completed.
15. Article 1 of the Contract provides definitions wherein Article 1.[8] gives the definition of project which reads as under: “1.[8] "PROJECT" shall mean the Housing Complex/ Urban Development at location (s) for which consultant is to provide SERVICES under this CONTRACT”
16. In any event, the interpretation of Article 17 of the Contract as to whether the cause of action arises or not would be a subject matter for the Arbitrator to decide.
17. The Apex Court in Interplay Between Arbitration Agreements under Arbitration, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1, has observed as under:
1997) 666.] On the other hand, Section 16 provides that the Arbitral Tribunal can “rule” on its jurisdiction, including the existence and validity of an arbitration agreement. A “ruling” connotes adjudication of disputes after admitting evidence from the parties. Therefore, it is evident that the Referral Court is only required to examine the existence of arbitration agreements, whereas the Arbitral Tribunal ought to rule on its jurisdiction, including the issues pertaining to the existence and validity of an arbitration agreement. A similar view was adopted by this Court in Shin-Etsu Chemical Co. Ltd. v. Aksh Optifibre Ltd. [Shin-Etsu Chemical Co. Ltd. v. Aksh Optifibre Ltd., (2005) 7 SCC 234]” (emphasis supplied)
18. Similarly, the Apex Court in SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 SCC OnLine SC 1754, has observed as under:
19. The issues as to whether the completion of work would include the defect liability period or not would also be a matter to be decided by the Arbitrator. It is well settled that the referral Court only sees as to whether dispute exists between the parties or not. In view of the fact that work stands completed, a Completion Certificate has been issued, disputes have arisen between the parties regarding the payment of money and the Contract has not been terminated, the present Petition deserves to be allowed.
20. Accordingly, Mr. Ashim Vacher, Sr. Advocate (Mob. No:
9811023217) is appointed as the Sole Arbitrator to adjudicate upon the disputes between the parties.
21. The arbitration would take place under the aegis of the Delhi International Arbitration Centre (DIAC) and would abide by its rules and regulations. The learned Arbitrator shall be entitled to fees as per the Schedule of Fees maintained by the DIAC.
22. The learned Arbitrator is also requested to file the requisite disclosure under Section 12(2) of the 1996 Act within two weeks of entering on reference.
23. All rights and contentions of the parties in relation to the claims/counter-claims are kept open, to be decided by the learned Arbitrator on their merits, in accordance with law.
24. Needless to state, nothing in this Order shall be construed as an expression of this Court on the merits of the contentions advanced on behalf of the parties.
25. The Petition stands disposed of in the above terms, along with pending application(s), if any.
SUBRAMONIUM PRASAD, J FEBRUARY 06, 2026