Full Text
HIGH COURT OF DELHI
Date of Decision: 13th February, 2026
KAAYA BUILDTECH PRIVATE LTD .....Petitioner
Through: Mr. Harshit Batra and Ms. Tanya Karnwal, Advs.
Through: Mr. Niraj Kumar, Sr. Central Govt.
Counsel with Mr. Chaitanya Kumar, Adv. for R1
Mr. Sanjay Kumar Pathak, SC with Mr. Sunil Kumar Jha, Mr. Mohd Sueb
Akhtar, Advs. for LAC
JUDGMENT
1. This hearing has been done through hybrid mode.
2. The present petition has been filed by the Petitioner under Article 226 of the Constitution of India, inter alia, seeking issuance of an appropriate writ directing the Respondents to refer the dispute regarding the enhancement of compensation awarded to the Petitioner under Award Nos. 02/2022/SW, 4/2022/SW and 7/2020/SW to arbitration under Section 3G(5) of the National Highways Act, 1956
3. A large passage of land was acquired under the National Highway Act, 1956 between the year 2020 and 2022 for development of National Highway being NH 334(M) and NH 334(N) in South West District, Delhi. The compensation was assessed and the same was paid to the Petitioner. However, the Petitioner was not satisfied with the compensation and on the ground that the same was not commensurate with the market value, the Petitioner had reserved its rights to seek enhanced compensation and prayed that the matter be referred to arbitration under Section 3G(5) of the National Highways Act,
1956.
4. The said request was made to the Special Secretary, Land and Building Department, GNCTD. However, despite reminders, the matter was not referred to arbitration. Hence, the present writ petition.
5. Ld. Counsel for the Petitioner submits that under Section 3G(5) of the National Highways Act, 1956, the Petitioner’s claim is liable to be referred to arbitration to the Special Secretary, as notified by the Government.
6. Ld. Counsel for the Petitioner has also placed reliance upon the decision in General Manager (Project) v. Prakash Chand Pradhan, Civil Appeal No. 5250 of 2018, wherein it was held that in such cases, the appropriate remedy is a writ petition. The said decision dated 16th May, 2018 is set out below: “Section 3-G of the National Highways Act, 1956 provides for determination of the amount that is payable by way of compensation. We are concerned in these appeals with sub-sections (5) and (6) of Section 3-G which read as under: "(5) If the amount determined by the competent authority under sub-section (1) or sub-section (2) is not acceptable to either of the parties, the amount shall, on an application by either of the parties, be determined by the arbitrator to be appointed by the Central Government. (6) Subject to the provisions of this Act, the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) shall apply to every arbitration under this Act." A cursory reading of sub-section (5) shows us that appointment of the arbitrator under the said sub-section is only in the hands of the Central Government. Sub-section (6) begins with the important expression "subject to the provisions of this Act", the provisions of the Arbitration and Conciliation Act, 1996 shall apply. Having heard learned counsel for the parties, we are, therefore, of the view that a Section 11 application under the 1996 Act cannot be made as the Central Government alone is to determine who is to be an arbitrator under Section 3-G (5) of the National Highways Act. If a demand is made for the appointment of an arbitrator, and the Central Government does not appoint an arbitrator within a reasonable time, the remedy that is to be availed of is a writ petition or a suit for the said purpose, and not Section 11 of the Arbitration and Conciliation Act, 1996. A similar provision contained in Section 86 (1)(f) of the Electricity Act, 2003 specifically gives the State Commission power to refer any dispute for arbitration. In this view of the matter, this Court in Gujarat Urja Vikas Nigam Ltd. vs. Essar Power Ltd., (2008) 4 SCC 755, held as under:
We respectfully agree with the ratio of the said judgment. Likewise, Section 3-G of the National Highways Act is a special provision which will be given effect insofar as the appointment of an arbitrator is concerned. Learned counsel appearing on behalf of the respondents has, however, argued that an arbitrator has now been appointed under Section 11 of the Arbitration and Conciliation Act, 1996 and, that, therefore, no prejudice will be caused if he is allowed to continue. This arguments ignores the fact that Section 11 of the Arbitration and Conciliation Act does not apply and that, under Section 3-G, the Central Government alone can appoint an arbitrator. Accordingly, the impugned judgment is set aside and the appeals are allowed.”
7. Mr. Pathak, ld. Counsel for the LAC submits that a communication has been written by the Petitioner directly to the Special Secretary by the Petitioner, who is not a Competent Authority since the Special Secretary has to himself act as the Arbitrator.
8. The Court has considered the matter. Section 3G (5) of the National Highways Act, 1956 provides as under: “[3G. Determination of amount payable as compensation.—... xxxx (5) If the amount determined by the competent authority under sub-section (1) or sub-section (2) is not acceptable to either of the parties, the amount shall, on an application by either of the parties, be determined by the arbitrator to be appointed by the Central Government--”
9. The Supreme Court in the decision in NHAI v. Sayedabad Tea Co. Ltd., (2020) 15 SCC 161 while dealing with the question whether an application under Section 11 of the Arbitration and Conciliation Act, 1996 is maintainable in view of Section 3G(5) of the National Highways Act, 1956, held as under:
21. In our considered view, the High Court of Calcutta was not holding its competence to appoint an arbitrator invoking Section 11 of the 1996 Act.
22. This very question earlier arose before this Court whether the application under Section 11(6) of the 1996 Act is maintainable in view of statutory provisions of the Electricity Act, 2003 adjudicating the dispute between the licensees and the generating companies of the special enactment and Section 86(1) of the Electricity Act, 2003 in particular, this Court in Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd. [Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd., (2008) 4 SCC 755] in para 28 observed as under: (SCC p. 765) “28. Section 86(1)(f) is a special provision and hence will override the general provision in Section 11 of the Arbitration and Conciliation Act, 1996 for arbitration of disputes between the licensee and generating companies. It is well settled that the special law overrides the general law. Hence, in our opinion, Section 11 of the Arbitration and Conciliation Act, 1996 has no application to the question who can adjudicate/arbitrate disputes between licensees and generating companies, and only Section 86(1)(f) shall apply in such a situation.”
23. We are also of the considered opinion that in view of the power being vested exclusively with the Central Government to appoint an arbitrator under Section 3- G(5) of the 1956 Act, being a special enactment, the application filed under Section 11(6) of the 1996 Act for appointment of an arbitrator was not maintainable and provisions of the 1996 Act could not be invoked for the purpose.”
10. In Bhupender Kumar Arora (HUF), Through its Karta Sh. Bhupender Kumar Arora v. Union of India & Anr., 2025: DHC:7774 a Ld. Single Judge of this Court, has held that the National Highways Act, 1956, being a special enactment, provides an inbuilt mechanism for the appointment of an Arbitrator by the Central Government under Section 3G(5). Consequently, Section 11 of the Arbitration and Conciliation Act, 1996 is inapplicable, and the authority to appoint an Arbitrator is exclusively vested in the Central Government. The relevant portion of the said decision reads as under:
21. In our considered view, the High Court of Calcutta was not holding its competence to appoint an arbitrator invoking Section 11 of the 1996 Act.
22. This very question earlier arose before this Court whether the application under Section 11(6) of the 1996 Act is maintainable in view of statutory provisions of the Electricity Act, 2003 adjudicating the dispute between the licensees and the generating companies of the special enactment and Section 86(1) of the Electricity Act, 2003 in particular, this Court in Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd. [Gujarat Urja Vikas Nigam Ltd. v. Essar Power Ltd., (2008) 4 SCC 755] in para 28 observed as under: (SCC p. 765) “28. Section 86(1)(f) is a special provision and hence will override the general provision in Section 11 of the Arbitration and Conciliation Act, 1996 for arbitration of disputes between the licensee and generating companies. It is well settled that the special law overrides the general law. Hence, in our opinion, Section 11 of the Arbitration and Conciliation Act, 1996 has no application to the question who can adjudicate/arbitrate disputes between licensees and generating companies, and only Section 86(1)(f) shall apply in such a situation.”
23. We are also of the considered opinion that in view of the power being vested exclusively with the Central Government to appoint an arbitrator under Section 3-G(5) of the 1956 Act, being a special enactment, the application filed under Section 11(6) of the 1996 Act for appointment of an arbitrator was not maintainable and provisions of the 1996 Act could not be invoked for the purpose.””
11. On a query from the Court, the ld. Counsel have informed that the question as to whether the appointment of the Special Secretary would be hit by Section 12(5) of the Arbitration & Conciliation Act, 1996 is also presently pending consideration in some cases before the Hon’ble Supreme Court. Ld. Counsel further submit that as of now arbitrations are being conducted by the Special Secretary as per the provision.
12. In view thereof, the Respondent No. 2 - Competent Authority (Land Acquisition)/CALA shall make the reference to arbitration within a period of 30 days in accordance with law.
13. A copy of this order be communicated to Respondent No. 2 - Competent Authority (Land Acquisition)/CALA formally by the Petitioner within a period of one week. The reference shall be made by the said Respondent No. 2 within 30 days thereafter.
14. The Court has been assured by Mr. Pathak, ld. Counsel for the LAC that the post of the Special Secretary, who has to act as an Arbitrator has now been filled up.
15. No further orders are called for in the present petition.
16. The petition is disposed of in the above terms. Pending applications, if any, are also disposed of.
PRATHIBA M. SINGH JUDGE MADHU JAIN JUDGE FEBRUARY 13, 2026/ys/ck