The Delhi High Court allowed the appeal to enhance compensation by 10% over the Reference Court's market value assessment for Village Bijwasan, following its prior ruling in Ranbir Sharma vs. Union of India.

Full Text
Translation output
C
1-13 HIGH COURT OF DELHI
LA.APP.45/2013
UOI Appellant
Through: Mr.Yeeshu Jam, Advocate.
VERSUS
KARTAR SINGH AND ORS Respondents
Through: Mr.D.K.Singh, Advocate for
• the
CORAM:
HON'BLE MS. JUSTICE REVA KHETRAPAL
26.02.2013
CMNQ.3412/2013
The prayer in the present application is for condonation of 136 days delay in filing the Appeal. Delay condoned.
Application stands disposed of.

CM No.3413/2013 Q The prayer in the present application is for extension of time for filing Court Fees. The Appellant is directed to deposit the same within two weeks.
Application stands disposed of.
LA.APP. 45/2013
ORDER

1. The learned counsel for the Appellant states that the present Appeal is covered by the judgment of this Court rendered in "Ranbir Sharma Vs. Union of India and 2013:DHC:8477 H Anr" reported in 187 (2012) DLT 781. In the said case the Appeals were partly allowed to the extent of awarding 10% increase over and above the market value assessed by the Reference Court in matters pertaining to Village Bharthal, Village Bijwasan and Village Pochanpur. The present case relates to Village Bijwasan and accordingly 10% increase is to be allowed in the present case as well. In view of the aforesaid)theAppeal is allowed in terms of. the judgment of thisCourt in the case of Ranbir Sharma (supra). Appellant is directed to deposit the enhanced compensation with the Reference Court within three weeks from today. LA.APP. 45/20 13 stands disposed of in the above terms. CM No.3411/2013 1ismissed as infructuous. REVA KIIETRAPAL, J. FEBRUARY 269 2013