Rajender Prasad v. Government of NCT of Delhi

Delhi High Court · 06 May 2025 · 2025:DHC:3912
Purushaindra Kumar Kaurav
ARB.P. 174/2025
2025:DHC:3912
civil petition_allowed Significant

AI Summary

The Delhi High Court held that at the Section 11 stage, the court's role is limited to prima facie existence of an arbitration agreement and appointed a sole arbitrator to adjudicate the dispute, leaving merits and limitation issues to arbitration.

Full Text
Translation output
HIGH COURT OF DELHI
ARB.P. 174/2025
Date of Decision: 06.05.2025 IN THE MATTER OF:
RAJENDER PRASAD .....Petitioner
Through: Mr. K. Prabhat and Mr. Bhola Dayar, Advs.
VERSUS
GOVERNMENT OF NCT OF DELHI .....Respondent
Through: Mr. Tushar Sannu, Adv. for GNCTD
WITH
Mr. Shivam and Mr. Aman, Advs.
CORAM:
HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
JUDGEMENT
PURUSHAINDRA KUMAR KAURAV, J. (ORAL)
JUDGMENT

1. Heard learned counsel appearing for the parties.

2. The petitioner in the instant petition has prayed for the following reliefs: “(a) Appoint independent and impartial Sole Arbitrator for adjudicating the dispute between the Petitioner and the Respondents in accordance with the terms of Agreement.”

3. As per the case set up by the petitioner, it is seen that the respondent had awarded him the contract for repair work relating to the footpath and drain at (i) Road No. 41, Punjabi Bagh and (ii) the road from House No. 250 KUMAR KAURAV to Shiv Mandir Road, under Sub-Division WR-24, during the financial year 2017–18 in New Delhi.

4. According to the petitioner, the assigned work was duly executed; however, the respondent failed to make full payment of the contractual dues. The petitioner subsequently issued a demand notice dated 11.02.2024 seeking payment. Despite receipt of the notice, the respondent did not take any steps in furtherance of settlement. Accordingly, the petitioner invoked the arbitration clause (Clause 25 of the Agreement) vide notice dated 22.04.2024.

5. In the absence of any response or initiative by the respondent following the invocation notice, the petitioner was constrained to file the present petition under Section 11 of the 1996 Act.

6. Upon issuance of notice, the respondent has entered appearance and filed its objections. The respondent disputes the maintainability of the petition and the entitlement of the petitioner to any relief. It is the respondent’s case that the claim raised by the petitioner is ex facie barred by limitation. Apart from the plea of limitation, the respondent has raised several other objections, which are not being detailed herein for the sake of brevity.

7. I have heard the learned counsel appearing for the parties and perused the record.

8. The Court has considered Clause 25 of the Agreement, which reads as under:- “CLAUSE 25 Except where otherwise provided in the contract, all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right, matter or thing whatsoever in any way arising out of or relating to the contract, designs, drawings, specifications, estimates, instructions, orders of these conditions or otherwise concerning the works or the execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter:

(i) If the contractor considers any work demanded of him to be outside the requirements of the contract, or disputes any drawings, record or decision the Engineer-In-Charge on any matter in connection with or arising out of the contract or carrying out of the work, to be unacceptable, he shall promptly within IS days request the Superintending Engineer in writing for written instruction or decision. Thereupon, the Superintending Engineer shall give his written instructions or decision within a period of one month from the receipt of the contractor's letter. If the Superintending Engineer fails to give his instructions or decision in writing within the aforesaid period of the contractor is dissatisfied with the instructions or decision of the Superintending Engineer, the contractor may, within IS days of the receipt of Superintending Engineer‟s decision, appeal to the Chief Engineer who shall afford an opportunity to the contractor to be heard, if the latter so desires, and to offer evidence in support of his appeal, The Chief Engineer shall give his decision within 30 days of receipt of contractor's appeal. If the contractor is dissatisfied with the decision of the Chief Engineer, the contractor may within 30 days from receipt of the Chief Engineer decision, appeal before the Dispute Redressal Committee (DRC) along with a list of disputes with amounts claimed in respect of each such dispute and giving reference to the rejection of his disputes by the Chief Engineer. The Dispute Redressal Committee (DRC) shall give his decision within a period of 30 days from the receipt of Contractor‟s appeal. The constitution of Dispute Redressal committee (DRC) shall be as indicated in Schedule „F‟. If the Dispute Redressal Committee (DRC) foils to give his decision within the aforesaid period or any party is dissatisfied with the decision of Dispute Redressal Committee (DRC), then either party may within a period of 30 days from the receipt of the decision of Dispute Redressal Committee (DRC), give notice to the Chief Engineer for appointment of arbitrator on prescribed proformo as per Appenclix XV, fulling which the said decision shall be final binding and conclusive and not referable to adjudication by the arbitrator. It is a term of contract that each party invoking arbitration must exhaust the aforesaid mechanism of settlement of claims/disputes prior to invoking arbitration.

(ii) Except where the decision has become Jinal, binding and conclusive in terms of Sub para (i) above, disputes or difference shall be referred for adjudication through arbitration by a sole arbitrator appointed by the Chief Engineer, CPWD, in charge of the work or if there be no Chief Engineer, the Additional Director General of the concerned region of CPWD or if there be no Additional Director General, the Special Director General or the Director General, CPWD. If the arbitrator so appointed is unable or unwilling to act or resigns his appointment or vacates his office due to any reason whatsoever, another sole arbitrator shall be appointed in the manner aforesaid. Such person shall be entitled to proceed with the reference from the stage at which it was left by his predecessor. It is a term of this contract that the party invoking arbitration shall give a list of disputes with amounts claimed in respect of each such dispute along with the notice for appointment of arbitrator and giving reference to the rejection by the Chief Engineer of the appeal. It is also a term of this contract that no person, other than a person appointed by such Chief Engineer CPWD or Additional Director General or Special Director General of Director General, CPWD, as aforesaid, should act as arbitrator and if for any reason that is not possible, the matter shall not be referred to arbitration at all. It is also a term of this contract that if the contractor does not make any demand for appointment of arbitrator in respect of any claims in writing as aforesaid within 120 days of receiving the intimation from the Engineer-In-Charge that the final bill is ready for payment the claim of the contractor shall be deemed to have been waived and absolutely barred and the Government shall be discharged and released of all liabilities under the contract in respect of these claims. The arbitration shall be conducted in accordance with the provisions of the Arbitration and conciliation Act, 1996 (26 of 1996) or any statutory modifications or re- enactment thereof and the rules made thereunder and for the time being in force shall apply to the arbitration proceeding under this clause, It is also a term of this contract that the arbitrator shall adjudicate on only such disputes as are referred to him by the appointing authority and give separate award against each dispute and claim referred to him and in all cases where the total amount of the claims by any party exceeds Rs.1,00,000/-, the arbitrator shall give reasons for the award. It is also a term of the contract that if any fees are payable to the arbitrator, these shall be paid equally by both the parties. It is also a term of the contract that the arbitrator shall be deemed to have entered on the reference on the date he issues notice to both the parties calling them to submit their statement of claims and counter statement of claims, The venue of the arbitration shall be such place as may be fixed by the arbitrator in his sole discretion. The fees, if any, of the arbitrator shall, if required to be paid before the award is made and published, be paid half and half by each of the parties. The cost of the reference and of the award (including the fees, tf any, of the arbitrator) shall be in the discretion of the arbitrator who may direct to any by whom and in what manner, such costs or any part thereof shall be paid and fix or settle the amount of costs to be so paid.”

9. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. This Court as well in the order dated 24.04.2025 in case of ARB.P. 145/2025 titled as Pradhaan Air Express Pvt Ltd v. Air Works India Engineering Pvt Ltd has extensively dealt with the scope of interference at the stage of Section 11. The Court held as under:-

9. The law with respect to the scope and standard of judicial scrutiny under Section 11(6) of the 1996 Act has been fairly well settled. The Supreme Court in the case of SBI General Insurance Co. Ltd. v. Krish Spinning,[1] while considering all earlier pronouncements including the Constitutional Bench decision of seven judges in the case of Interplay between Arbitration Agreements under the Arbitration & Conciliation Act, 1996 & the Indian Stamp Act, 1899, In re 2 has held that scope of inquiry at the stage of appointment of an Arbitrator is limited to the extent of prima facie existence of the arbitration agreement and nothing else.

10. It has unequivocally been held in paragraph no.114 in the case of SBI General Insurance Co. Ltd that observations made in Vidya Drolia v. Durga

Trading Corpn.,[3] and adopted in NTPC Ltd. v. SPML Infra Ltd.,[4] that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would not apply after the decision of Re: Interplay. The abovenoted paragraph no.114 in the case of SBI General Insurance Co. Ltd reads as under:-

“114. In view of the observations made by this Court in In Re: Interplay (supra), it is clear that the scope of enquiry at the stage of appointment of arbitrator is limited to the scrutiny of prima facie existence of the arbitration agreement, and nothing else. For this reason, we find it difficult to hold that the observations made in Vidya Drolia (supra) and adopted in NTPC v. SPML (supra) that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non-arbitrable and frivolous disputes would continue to apply despite the subsequent decision in In Re: Interplay (supra).”
16,149 characters total

11. Ex-facie frivolity and dishonesty are the issues, which have been held to be within the scope of the Arbitral Tribunal which is equally capable of deciding upon the appreciation of evidence adduced by the parties. While considering the aforesaid pronouncements of the Supreme Court, the Supreme Court in the case of Goqii Technologies (P) Ltd. v. Sokrati Technologies (P) Ltd.,[5] however, has held that the referral Courts under Section 11 must not be misused by one party in order to force other parties to the arbitration agreement to participate in a time-consuming and costly arbitration process. Few instances have been delineated such as, the adjudication of a non-existent and malafide claim through arbitration. The Court, however, in order to balance the limited scope of judicial interference of the referral Court with the interest of the parties who might be constrained to participate in the arbitration proceedings, has held that the Arbitral Tribunal eventually may direct that the costs of the arbitration shall be borne by the party which the Arbitral Tribunal finds to have abused the process of law and caused unnecessary harassment to the other parties to the arbitration.

12. It is thus seen that the Supreme Court has deferred the adjudication of aspects relating to frivolous, non-existent and malafide claims from the referral stage till the arbitration proceedings eventually come to an end. The relevant extracts of Goqii Technologies (P) Ltd. reads as under:-

“20. As observed in Krish Spg. [SBI General Insurance Co. Ltd. v. Krish Spg., (2024) 12 SCC 1 : 2024 SCC OnLine SC 1754 : 2024 INSC 532] , frivolity in litigation too is an aspect which the referral court should not

decide at the stage of Section 11 as the arbitrator is equally, if not more, competent to adjudicate the same.

21. Before we conclude, we must clarify that the limited jurisdiction of the referral courts under Section 11 must not be misused by parties in order to force other parties to the arbitration agreement to participate in a time consuming and costly arbitration process. This is possible in instances, including but not limited to, where the claimant canvasses the adjudication of non-existent and mala fide claims through arbitration.

22. With a view to balance the limited scope of judicial interference of the referral courts with the interests of the parties who might be constrained to participate in the arbitration proceedings, the Arbitral Tribunal may direct that the costs of the arbitration shall be borne by the party which the Tribunal ultimately finds to have abused the process of law and caused unnecessary harassment to the other party to the arbitration. Having said that, it is clarified that the aforesaid is not to be construed as a determination of the merits of the matter before us, which the Arbitral Tribunal will rightfully be equipped to determine.”

13. In view of the aforesaid, the scope at the stage of Section 11 proceedings is akin to the eye of the needle test and is limited to the extent of finding a prima facie existence of the arbitration agreement and nothing beyond it. The jurisdictional contours of the referral Court, as meticulously delineated under the 1996 Act and further crystallised through a consistent line of authoritative pronouncements by the Supreme Court, are unequivocally confined to a prima facie examination of the existence of an arbitration agreement. These boundaries are not merely procedural safeguards but fundamental to upholding the autonomy of the arbitral process. Any transgression beyond this limited judicial threshold would not only contravene the legislative intent enshrined in Section 8 and Section 11 of the 1996 Act but also risk undermining the sanctity and efficiency of arbitration as a preferred mode of dispute resolution. The referral Court must, therefore, exercise restraint and refrain from venturing into the merits of the dispute or adjudicating issues that fall squarely within the jurisdictional domain of the arbitral tribunal. It is thus seen that the scope of enquiry at the referral stage is conservative in nature. A similar view has also been expressed by the Supreme Court in the case of Ajay Madhusudan Patel v. Jyotrindra S. Patel[6].

14. In view of the fact that disputes have arisen between the parties and there is an arbitration clause in the contract, this Court is inclined to appoint a Sole Arbitrator to adjudicate upon the disputes.

15. Accordingly, Mr. Rakesh Kumar Dudeja, Advocate (Mobile no. +91-

16. The arbitration would take place under the aegis of the Delhi International Arbitration Centre (DIAC) and would abide by its rules and regulations. The learned Arbitrator shall be entitled to fees as per the Schedule of Fees maintained by the DIAC.

17. The learned arbitrator is also requested to file the requisite disclosure under Section 12 (2) of the 1996 Act within a week of entering on reference.

18. The registry is directed to send a receipt of this order to the learned arbitrator through all permissible modes, including through e-mail.

19. All rights and contentions of the parties in relation to the claims/counter-claims are kept open, to be decided by the learned Arbitrator on their merits, in accordance with law.

20. The petition stands disposed of in the aforesaid terms.

PURUSHAINDRA KUMAR KAURAV, J MAY 6, 2025/P/SP